VIDEO: Sydney Metro bids thanks and farewell to the Sydney Monorail, Transport for NSW (31 Aug 2017)

This is an updated version of a previous post from March 2016.

Below is a list of all the railways that Sydney might expect in the near future. It only includes heavy rail (i.e. Sydney Trains or Sydney Metro, but not light rail) and includes both new lines or extensions to existing lines. Railways must have been proposed by the state or federal government, so any railways proposed only by local councils or lobby groups are not included nor any railways mentioned exclusively in internal government documents not intended for public release. Also excluded are railways previously announced but since cancelled.

Under construction: Sydney Metro Northwest

The current incarnation of this line was announced in 2010, with construction commencing in 2014. It is scheduled to open in 2019. This line consists of 23km of new track between Epping and Cudgegong Rd near Rouse Hill as well as the conversion of the existing 13km Epping to Chatswood Line (opened in 2009) to metro operation.

A line with a similar alignment was originally announced in 1998 (connecting to the Northern Line at Eastwood rather than Epping), but cancelled in 2008 in favour of a metro line that was itself also cancelled. It has previously been known as the North West Rail Link and Sydney Rapid Transit.

2015-02-20 NWRL

Alignment of the Sydney Metro Northwest from Cudgegong Rd to Chatswood. Click to enlarge. (Source: Transport for NSW.)

Under construction: Sydney Metro City and Southwest

This line was announced in 2014, with construction commencing in 2017. It is scheduled to open in 2024. This line consists of 13km of new track between Chatswood and Sydenham as well as the conversion of the existing 17km Bankstown Line between Sydenham and Bankstown to metro operation.

Sydney Metro City and Southwest Alignment 2016

Sydney Metro City and Southwest alignment. Click to enlarge. (Source: Transport for NSW.)

Announced: Sydney Metro West

This line was announced in 2016, with no date currently set for construction to commence. It is scheduled to open in the second half of the 2020s, though the government is understood to be keen to fast track a 2026 opening date. Stations have been confirmed for Parramatta, Sydney Olympic Park, the bays precinct, and the Sydney CBD.

Four options are currently being considered, with a Metro Rapid option firming as the favourite providing the highest benefit-cost ratio. This option involves a 20 minute journey between Parramatta and the Sydney CBD, with trains travelling between 10 stations at up to 130km/hour, with a benefit-cost ratio of 2.5.

UPDATE: However, the favoured option appears to be the Metro Local South. This option involves a 25 minute journey between Parramatta and the Sydney CBD, with trains travelling between 12 stations at up to 100km/hour, with a benefit-cost ratio of 2.3 when the sale of air rights to development above stations is taken into account.

2016-10-18-west-metro-and-cbd-metro-alignment

Planned route of the 2008 West Metro, which may be indicative of the future Sydney Metro West. Click to enlarge. (Source: Railway Gazette)

Announced: Leppington to St Marys extension

Technically not yet announced, the government is understood to be about to announce an extension of the existing T2 Line from Leppington to the T1 Line at St Marys via a new Western Sydney Airport at Badgerys Creek. Previous investigations into an extension of the South West Rail Link from Leppington also included a Southern extension to Narellan. This extension provides the greatest potential for a freight rail connection to the new airport, whereas a metro connection would be unlikely to provide the opportunity for freight trains to reach the new airport.

2014-05-04 swrl-extension-corridor-map

The proposed corridors for an extension of the SWRL through to Badgerys Creek and beyond. Click to enlarge. (Source: Transport for NSW.)

NSW Premier Gladys Berejiklian has indicated her preference is for a rail connection after the airport opens and further commented that “Some major airports around the world take up to 10 years to build a rail line”. With a 2026 scheduled opening date for a Western Sydney Airport, this would suggest a 2026-36 opening date for an airport railway.

Meanwhile, Federal Opposition Leader Bill Shorten announced his support in April 2017 for a North-South rail connection, but went further in calling for it to be completed in time for the opening of a Western Sydney Airport in 2026. So although there is a difference in opinion on timing, there is now bipartisanship support for a rail line connecting the airport to Leppington and St Marys.

Proposed: Cudgegong Rd to Marsden Park extension

Work on preserving a corridor to extend the Sydney Metro Northwest began before construction on the line had even begun. Two options were considered: a Northern extension to Riverstone and a Western extension to Marsden Park via Schofields. The latter option was chosen with the potential to extend it further to the Mount Druitt area, although the corridor is to be reserved with mode neutrality. In other words, it could be both as an extension of Sydney Metro, but it could also be built as even bus rapid transit/light rail or even heavy rail with double deck trains from the T1 Western Line at Mount Druitt or St Marys.

NWRL Extension Corridor Options

Two options exist for linking the NWRL to the Richmond Line. One goes North West to Vineyard, the other continues west through Schofields and towards Marsden Park. Click to enlarge. (Source: http://northwestoptions.com.au)

Proposed: Bankstown to Liverpool extension

This proposal would see the Sydney Metro extended from the currently planned terminus at Bankstown out to Liverpool.

Such a line could link both Bankstown and Liverpool to Bankstown Airport, allowing for potential redevelopment of the current airport site. That would be in line with the Government´s pattern of building new transport infrastructure in places that enable new developments, including Waterloo, Sydney Olympic Park, the Bays Precinct, or the proposed redevelopment of Long Bay Prison. It would also provide connections between Liverpool and the Sydney CBD via Bankstown that are set to be lost once the Bankstown Line is converted to Metro services by 2024.

VIDEO: Sydney Metro: Future Options – Bankstown to Liverpool (Transport for NSW)

Proposed: Parramatta to Western Sydney Airport extension

A Western extension to the Sydney Metro West, this line would link up Parramatta with a Western Sydney Airport at Badgerys Creek. With the airport and metro line each scheduled to open in 2026 or later, much of

Prime Minister Malcolm Turnbull has called for a rail link to the airport to be built by the year 2046, but not necessarily ready to open simultaneously with a Western Sydney Airport. However, this was before the NSW Government opted for a North-South rail link from Leppington to St Marys, which is set to be announced jointly with the federal government.

2016-03-12 Parramatta Fast Rail Route

Potential alignments for a fast rail connection from Parramatta to a Western Sydney Airport at Badgeries Creek and the Sydney CBD. Click to enlarge. (Source: Parramatta City Council, Western Sydney Airport Fast Train – Discussion Paper, page 12.)

Proposed: City to Long Bay extension

An Eastern extension of the Sydney Metro West, this line would link up the Sydney CBD to the South East along a former tram reservation on Anzac Parade. To this date, there is no official government proposal for this line, only an unsolicited proposal from 2016.

However, Infrastructure NSW has been investigating the Anzac Parade corridor since 2014. The plans would involve the sale of the Long Bay Prison for redevelopment, which itself would help to fund the construction costs of a rail line down that corridor. This is in line with similar plans for Waterloo, the Bays Precinct and Sydney Olympic Park where new metro lines would support redevelopment that would in turn be enabled by the new metro line.

So far, this corridor has been investigated for an extension of the currently under construction light rail line out to Kingsford. Despite this, the close correlation between the unsolicited proposal and line actually being planned at the moment are close enough that an extension to La Perouse via Long Bay appears like a good proxy for official government policy.

2017 timetable (part 2): Off peak

Posted: September 4, 2017 in Transport
Tags: ,

VIDEO: More than 1,500 extra weekly services for train customers, Transport for NSW (28 August 2017)

See also: 2017 timetable (part 1): Morning peak

The number of stations with a train service every 15 minutes is set to rise from 88 to 126 (representing 71% of the networks 178 stations), an increase of 43%, thanks to the addition of 1,500 additional weekly services as part of a timetable revamp set to be introduced in November. This has been achieved by adding additional services in some parts of the network and by re-scheduling services to be evenly spaced where there are already 4TPH (Trains Per Hour) on that part of the network. These 15 minute frequencies will last most of the day, 7 days a week. The government has touted the benefits of this as allowing users to ignore the timetable and instead just turn up and go.

To visualise what this means, compare the Sydney Trains map shown above to the one shown below. The map above is the normal network map, showing all the stations. The map below (the regular map, modified by this blog´s author) only shows the stations that currently receive 15 minute frequencies all day. Lines with turn up and go frequencies can be seen in Inner Sydney as well and Nothern Sydney: the T1 North Shore Line, T1 Northern Line, T1 Epping Line, T2 Inner West Line, T3 Bankstown Line, T4 Eastern Suburbs Line, and T8 Airport Line.

The map shown below also includes the stations that are set to get 15 minute frequencies in November. These new stations are mostly in Sydney´s West: the T1 Western Line, T2 Leppington Line, and T8 South Line. The main lines still missing a regular all day 15 minute frequency are the T1 Richmond Line, T4 Cronulla Line, and the T4 Illawarra Line. The T1 Richmond and T4 Illawarra Line are hampered by being branch lines that service sparsely populated areas, meanwhile the T4 Cronulla Line does have 4 trains per hour, but enter the city on 10/20 minute frequencies due to varied stopping patterns.

Additionally, where branch lines with 15 minute frequencies merge in the inner portions of the network it results in even higher frequencies. Most of these stations thus provide all day frequencies of a train every 10 minutes or less, with a few providing frequency levels of a train every 11 minutes or less (often in one direction rather than both directions). The highest frequencies are seen on the City Circle, where trains travelling through in a clockwise direction pass through stations every 6 minutes or less all day.

There are 3 areas in particular, accounting for 27 stations, where this occurs:

  1. The T4 Cronulla Line and T4 Illawarra Line merge at Sydenham to provide 6TPH, resulting in even 10 minute frequencies between Sydenham and Bondi Junction.
  2. The T8 Airport Line and T8 South Line merge at Wolli Creek to provide 8TPH, resulting in 6/9 minute frequencies between Wolli Creek and Central via the airport stations in both directions. Services through the City Circle, entering via Museum and travelling counter-clockwise, continue this 6/9 minute frequency.
  3. The T2 Leppington Line, T2 Inner West Line, and T3 Bankstown Line merge at Redfern to provide 12TPH, resulting in 3/6 minute frequencies through the City Circle, entering via Town Hall and travelling clockwise, though to Central.
  4. The T2 Leppington Line and T2 Inner West Line merge at Ashfield to provide 8TPH, resulting in either 7/8 minute or 4/11 minute frequencies into the City Circle for Ashfield and Newtown Stations. Frequency levels depend on direction of travel and whether it is a weekday or weekend. However, Newtown´s 15 minute frequencies remain on weekends.
  5. The T1 Western Line and T1 Epping Line merge at Strathfield to provide 8TPH, resulting in 6/9 minute or 4/11 minute frequencies into the City and through to Chatswood for Strathfield Station. Frequency levels depend on direction of travel.

The stations affected can be seen in the map below.

Commentary: Why frequency matters

This blog has argued the merits of high frequency networks before (see: here, here, here). A network of high frequency public transport services, buses as well as trains, with easy interchanges between them, allow for a much greater level of mobility for its users.

The big increase in the 15 minute turn up and go network is to be commended. This will go a long way to improving access to the Sydney CBD. But for users wanting to make a transfer at an interchange, be it catching a bus to their local station or changing trains at an outer suburban station, a 15 minute frequency is just too long.

That´s why identifying where services are more frequent than a train every 15 minute is so important. As it turns out, 27 stations in and near the city currently do; reaching Chatswood, Bondi Junction, Wolli Creek, and Strathfield. Most of these have gaps between train services of no more than 10 minutes, with the best service levels seen on the City Circle for anyone travelling through it on a clockwise direction of a train every 6 minutes or less all day.

But there is still scope for improvement that requires little to no additional spending on operating costs. Here are some suggestions:

  1. Re-schedule trains on T1 between Strathfield and Chatswood to eliminate the 11 minute gaps between some services. This would allow for a train every 9 minutes or less all day without having to add more trains.
  2. Look into making express trains on T2 stop at Newtown during weekends to give that station 8TPH across the full week. Both these changes may be possible without having to add more trains.
  3. Re-route trains on T3 to run through the City Circle via Museum and then terminate at Redfern where they can turn around at the Macdonaldtown turnback and return to Bankstown through the City Circle. This would increase frequencies through the City Circle up to 12TPH in both directions, providing a train every 6 minutes or less all day with only a small increase in cost.
  4. Re-schedule trains through the City Circle to have even spacings. Where there are 12TPH, this would mean a train every 5 minutes rather than 3/6/6 minute gaps in the frequency as is currently the case. It would result in 5/10 minute frequencies in other parts of the network, rather than 6/9 minute frequencies, such as the Airport Line.

In the longer term, the two new Sydney Metro Lines should result in a large increase to the all day high frequency network out to Rouse Hill, Parramatta, and Bankstown. Sydney Metro Northwest is currently slated to run at 10 minute frequencies all day. When it gets extended through to Bankstown increasing its frequencies up to a train every 5 minutes all day would be a big improvement that would achieve the earlier stated goal of providing a true turn up and go network that makes interchanges easy and seamless.

Two thirds of stations on the Sydney Trains network will enjoy a train to the city every 15 minutes during most hours of the day on both weekdays and weekends under a revamp of the train timetable set to be implemented in late November. The plans will also see a boost to peak hour services, with the number of trains entering Sydney´s CBD stations increasing to 114 during the busiest hour of the morning; a 3.6% increase on the existing 110 trains per hour, while Liverpool will see the addition of fast express trains into the city during the morning peak.

The new timetable is accompanied by a new network map (shown above), which was reviewed by the Transit Maps website.

All up, an additional 1,500 services are being added per week. Half of these during the weekend. For comparison, the 2013 timetable changes saw an increase of 700 services per week, with no change to the weekend timetable. The increase in service levels will be supported by a $1.5bn capital investment, the largest part of which will be the purchase of an additional 24 Waratah trains. This will increase the existing fleet of Waratahs trains from 78 to 102.

This post will look at how the changes affect the morning peak hour. A future post will focus at the off-peak.

The Good

The number of trains into the city from Parramatta is set to increase from 20TPH (Trains Per Hour) to 24TPH. If the 4TPH on the Blue Mountains Line which stop at Parramatta but terminate at Central´s Sydney Terminal are included, Parramatta will soon see 28TPH into Central Station during the busiest hour of the morning peak.

It achieves this by extending the T2 Inner West Line to Parramatta, with 4TPH on that line now starting at Parramatta rather than Homebush. This was one of the few ways to increase capacity into the city from Parramatta, as the Western Line is currently at maximum capacity of 20TPH.

The new timetable then resolves the issue of overcrowding on the T2 Line from additional passengers boarding at Parramatta by adding an adding additional capacity on the T2 Leppington Line and T3 Bankstown Line. It is able to do this as these both run into the City Circle, which is the only line with significant spare capacity. The City Circle currently uses 34 out of the 40 paths (that being 20TPH in each direction) available during the busiest hour of the morning peak. The new timetable adds an additional 4TPH into the city, meaning that 38 paths out of a potential 40 will now be used. As a result, the T3 Bankstown Line will see an increase from 8TPH to 10TPH, and the T2 Leppington And Inner West Line will see an increase from 12TPH to 14TPH. This should, in theory, offset the loss of 4TPH to Parramatta.

The Bad

The increase in services through the City Circle now mean that Sydney’s city stations are one step away from being full during peak hour, with 114 of the available 120 paths on the 3 CBD lines being used up. This is 95% of maximum capacity.

With demand on the rail network currently growing at a rate of 10% per year, there is a risk that the network will reach capacity well before additional rail capacity comes online in 7 years when the Sydney Metro is extended through under the CBD in 2024.

The only other viable stop gap would appear to be an increase in services into Sydney Terminal. Internal government plans prepared in 2014 show this could increase capacity into Central Station by 16% during the busy morning peak, but it would cut many direct services between the city and Sydney´s outer suburbs. The current timetable goes part of the way in doing this by rerouting some T1 Richmond Line services through to the T5 Cumberland Line, but for now Richmond retains direct services into the city.

The Ugly

The T2 and T3 lines will now have some very unusual stopping patterns during the morning peak. Some stations on theT3 Bankstown Line will now have a 19 minute gap between services during the morning peak. This seems designed to cater for the new Liverpool express services.

It is unusual because this undoes part of what the 2013 timetable changes aimed to do: simplify the timetable to create regular clockface timetable. Strangely, those same stations still enjoy regular 15-minute clock face frequencies during the off peak hours of the day.

To complicate things even further, there is a possibility that these unusual stopping patterns will not survive past 2024, when the Sydney Metro City and Southwest absorbs the Bankstown Line.