There are two rail lines in Sydney currently under construction or in the planning phase. The first is the Sydney Metro Northwest, announced in 2010 and set to open in 2019; it consists of 23km of new track between Epping and Cudgegong Rd near Rouse Hill as well as the conversion of the existing 13km Epping to Chatswood Line (opened in 2009) to metro operation. The second is the Sydney Metro City and Southwest, announced in 2014 and set to open in 2024; it consists of 13km of new track between Chatswood and Sydenham as well as the conversion of the existing 17km Bankstown Line between Sydenham and Bankstown to metro operation.

Although no firm plans are currently in place for expansion of the rail network beyond 2024, there are a number of rail lines that have been mentioned by state and federal Transport Ministers, Premiers, and Prime Ministers. In chronological order of their first announcement, these include an extension of the Sydney Metro from Cudgegong Rd to Marsden Park, an extension of the South West Rail Link to Badgerys Creek, an extension of the Sydney Metro from Bankstown to Liverpool, and a new fast train from Parramatta to the Sydney CBD and Badgerys Creek.

(Left out of this list are previously announced rail lines that have been raised in internal government documents or were official government policy but in either case have since been abandoned. These include the Parramatta to Epping Rail Link, a metro line to the Northern Beaches, a metro line to Hurstville, and an extension of the Eastern Suburbs Line to UNSW.)

Cudgegong Road to Marsden Park

Work on preserving a corridor to extend what was then known as the North West Rail Link, now Sydney Metro Northwest, began before construction on the line had even begun. Two options were considered: a Northern extension to Riverstone and a Western extension to Marsden Park via Schofields. The latter option was chosen with the potential to extend it further to the Mount Druitt area, although the corridor is to be reserved with mode neutrality. In other words, it could be both as an extension of Sydney Metro, but it could also be built as even bus rapid transit/light rail or even heavy rail with double deck trains from the T1 Western Line at Mount Druitt or St Marys.

NWRL Extension Corridor Options

Two options exist for linking the NWRL to the Richmond Line. One goes North West to Vineyard, the other continues west through Schofields and towards Marsden Park. Click to enlarge. (Source: http://northwestoptions.com.au)

Leppington to Badgerys Creek

The South West Rail Link would be extended from the current terminus at Leppington through to Badgerys Creek at the new Western Sydney Airport. This line would also include a potential extension North to St Marys and South to Narellan. By connecting to the existing heavy rail network, this line also provides the greatest potential for a freight rail connection to the new airport. However, it does not provide a fast nor a direct rail connection between the airport and Parramatta, the Sydney CBD, nor the existing Kingsford Smith Airport at Mascot.

The proposed corridors for an extension of the SWRL through to Badgerys Creek and beyond. Click to enlarge. (Source: Transport for NSW.)

The proposed corridors for an extension of the SWRL through to Badgerys Creek and beyond. Click to enlarge. (Source: Transport for NSW.)

This is also the only proposed new rail line that is an extension of the existing heavy rail network. All of the other 3 proposals involve extensions of the Sydney Metro network currently under construction or the creation of a new single deck fast train.

Bankstown to Liverpool

An extension of the Sydney Metro City and Southwest, set to open in 2024 between Chatswood and Bankstown via the Sydney CBD, this would see the line extended further out to Liverpool.

The proposed Southern extension of Sydney Metro would see the line extended from the currently planned terminus at Bankstown out to Liverpool. Click to enlarge. (Source: Transport for NSW.)

The proposed Southern extension of Sydney Metro would see the line extended from the currently planned terminus at Bankstown out to Liverpool. Click to enlarge. (Source: Transport for NSW.)

Such a line could link both Bankstown and Liverpool to Bankstown Airport, allowing for potential redevelopment of the current airport site into a new business park. It would also provide connections between Liverpool and the Sydney CBD via Bankstown that are set to be lost once the Bankstown Line is converted to Metro services at some point in the next 8 years.

VIDEO: Sydney Metro: Future Options – Bankstown to Liverpool (Transport for NSW)

Sydney to Parramatta

Parramatta City Council, in conjunction with the Western Sydney Business Chamber, have proposed a fast train from the Sydney CBD to Parramatta that would complete the journey in as little as 15 minutes. It also includes a Western Link between Parramatta and a future Western Sydney Airport at Badgerys Creek.

Potential alignments for a fast rail connection from Parramatta to a Western Sydney Airport at Badgeries Creek and the Sydney CBD. Click to enlarge. (Source: Parramatta City Council, Western Sydney Airport Fast Train - Discussion Paper, page 12.)

Potential alignments for a fast rail connection from Parramatta to a Western Sydney Airport at Badgeries Creek and the Sydney CBD. Click to enlarge. (Source: Parramatta City Council, Western Sydney Airport Fast Train – Discussion Paper, page 12.)

The Eastern Link has 4 potential alignments to Parramatta Station:

  1. Upgrading the existing surface rail corridor with stations at Central, Strathfield, and Lidcombe. This would not reduce travel times by more than a few minutes below the current 25 minute minimum. It would also do the least to add extra capacity.
  2. A tunnel underneath the existing rail corridor with stations at the future Sydney Metro Station in Pitt St, Croydon, and Lidcombe. This has longer journey times than Options 3 or 4 and has limited scope for value capture. However, it provides the most favourable tunneling conditions.
  3. A tunnel South of the Parramatta River with stations at the future Sydney Metro Station in Pitt St, White Bay, and Olypmic Park. This is the shortest and fastest option. It also has the best scope for value capture and most challenging tunneling conditions.
  4. A tunnel North of the Parramatta River with stations at the future Sydney Metro Station in Barangaroo, White Bay, and Ryde. This is longer than Option 3, but passes through more existing centres. It has less scope for value capture but better patronage in the medium term.

The Western Link has 2 potential alignments between Parramatta Station and Badgerys Creek:

  1. A Southern corridor with an intermediate station in Liverpool.
  2. A Northern corridor with an intermediate station in either Blacktown or near the M4/M7.

The Western Link has fewer details than the Eastern Link. Proponents are split over which section to build first, with Parramatta City Council CEO Greg Dyer supporting an Eastern Link and Parramatta MP Geoff Lee supporting a Western Link. Meanwhile, Prime Minister Malcolm Turnbull has called for a Western Link to be built earlier than 2046, but not necessarily ready to open simultaneously with a Western Sydney Airport. Sydney Morning Herald City Editor Jacob Saulwick argues that an Eastern Link is more pressing given the capacity constraints between Parramatta and the Sydney CBD, but that it would be a good stage one for when a future extension to Badgerys Creek becomes needed and built as stage two.

Note: For the second time this year, this blog has taken an unannounced hiatus for a number of months due to the pressures of real life. This post was written up at the end of June but never properly finished and thus not posted. It will probably be the final monthly round up, at least for the foreseeable future. This blog will not be ending, posts will still continue. But instead, the focus will be on specific issues or events as they occur with no set frequency of posts. For now, please enjoy the breaking news from 3 months ago…

VIDEO: Urban Taskforce Research- Who Lives in Apartments (31 May 2015)

2 June: $50m cost blowout for NWRL

The budget for constructing the skytrain portion of the North West Rail Link, an elevated viaduct between Bella Vista and Rouse Hill, has blown out from $340m to $390m. Despite the cost blowout, a project spokesperson said that there has been no change to the completion date for the skytrain, while the Transport Minister Andrew Constance stated that variations in cost had been factored into the full $8.3bn budget and that the overall budget remained unchanged.

The skytrain portion of Sydney Metro, shown at the proposed Rouse Hill Station. Click to enlarge. (Source: Transport for NSW.)

The skytrain portion of North West Rail Link, shown at the proposed Rouse Hill Station. Click to enlarge. (Source: Transport for NSW.)

 4 June: Sydney Rapid Transit renamed Sydney Metro

Sydney’s single deck train network will be known as Sydney Metro, replacing the previous name Sydney Rapid Transit. This follows the passage of legislation authorising the privatisation of state owned electricity assets, which passed both chambers of Parliament the previous day.

4 June: NSW Opposition dumps support for light rail because of Infrastructure NSW Report

The new Shadow Transport Minister Ryan Park, who together with the Opposition Leader Luke Foley recently withdrew their support for light rail down George Street, announced that the change of heart on light rail came after reading the 2012 Infrastructure NSW Report that opposed George Street light rail. The alternative bus tunnel option suggested by the report was criticised by Transport for NSW, with Infrastructure NSW later supporting George Street light rail.

A very early proposed map for the CBD BRT would see a tunnel between Wynyard and Town Hall, removing many buses from the surface streets. Click on image for higher resolution. (Source: First Things First, Infrastructure NSW, page 99.)

A very early proposed map for the CBD BRT would see a tunnel between Wynyard and Town Hall, removing many buses from the surface streets. Click to enlarge. (Source: First Things First, Infrastructure NSW, page 99.)

6 June: Transport corridors in Western Sydney to be reserved

Work to reserve transport corridors in Sydney’s West for an Outer Sydney Orbital motorway, Bells Line of Road to Castlereagh Connection, and South West Rail Link extension is moving into the public consultation phase. The NSW Roads Minister Duncay Gay said that work on the 2 roads was not expected to begin for decades; with the SWRL corridor set to be identified by late 2016.

8 June: Olympic Park becomes preferred light rail option

A light rail line connecting Parramatta to Olympic Park has firmed as the favourite option for a new light rail line in Sydney’s West. The line could extend out to Wesmead in the West and Strathfield in the East. It gained favour after a campaign by businesses and developers who touted the possibility for development of the corridor and the potential for value capture from that development to fund the cost of building the new line. However, local councils have labelled the line a white elephant and are calling for the Government to build a line to Epping instead.

11 June: Opal only gates installed at Wynyard Station

New Opal only gates have been installed as part of the Wynyard Station upgrade. Opal only gates have recently been installed at Olympic Park Station. No date has been set for the full phase out of ticket gates that accept magnetic stripe paper ticket.

12 June: SWRL connection to CBD via Granville?

Transport blogger Nick Stylianou suggests that Leppington trains may be connected up to the T2 South Line, travelling to the CBD via Granville. This may happen as soon as the end of this year, with Campbelltown to city services running exclusively on the T2 Airport Line.

12 June: 65 new transport officers

Sydney’s existing 150 transport officers is set to increase to 215, with an additional 65 transport officers to be hired.

15 June: Trial of backdoor boarding on CBD buses

The Government is set to trial boarding of buses via the back door for 2 weeks. The trial will be restricted to Opal card users between 4PM and 7PM at 7 bus stops in the CBD. Marshals will be present to ensure boarding occurs safely. It is hoped that the trial will see lower dwell times for buses by allowing customers to board more quickly.

VIDEO: Seven News Sydney – Trial of back door loading on buses (15/6/2015)

19 June: Reduction in minimum parking requirements

The NSW Government has announced a watered down version of a minimum parking requirement policy that it announced last year. The new policy allows new apartment blocks in areas well serviced by public transport to have fewer off-street parking spots than is currently mandated by local government regulations. The previously announced policy would have eliminated the requirement for off-street parking entirely and has not been adopted. Supporters of the move argue that it will help to keep construction costs down and help with housing affordability. Opponents of the move claim that it will cause cars to spill over into existing streets where parking is already scarce.

23 June: Barangaroo Station confirmed

A Station at Barangaroo has been confirmed in the Sydney Metro City and Southwest. Stations still to be determined are Artarmon, St Leonards/Crows Nest and either Sydney University or Waterloo.

VIDEO: Sydney Metro Barangaroo Station

The name Sydney Rapid Transit is no more, with the project to be renamed Sydney Metro. Its two component parts, the North West Rail Link and Second Harbour Rail Crossing are also getting new names; they will now be known as Sydney Metro Northwest and Sydney Metro City & Southwest respectively. The news comes in response to the passage of legislation through the NSW Parliament to allow the partial privatisation of the state’s electricity distribution network via a 99 lease of 49% of the business in order to provide funding for the second stage of the Sydney Metro project.

Sydney Metro Northwest is set to open in early 2019 with construction already underway; while Sydney Metro City & Southwest is set to open in 2024 with construction starting in 2017. The latter has 4 confirmed stations between Chatswood and Sydenham: Victoria Cross (North Sydney), Martin Place, Pitt Street (Town Hall), and Central. It will also include either an underground station at Crows Nest or an above ground station utilising the existing platforms at St Leonards, depending on where tunnels on the Northern end will emerge. The Sydney Metro website states that “options for where the tunnels start include just south of Chatswood or at St Leonards”, with a final decision yet to be made.

Sydney Metro proposed alignment. Click to enlarge. (Source: Project Overview, Sydney Metro.)

Sydney Metro proposed alignment. Click to enlarge. (Source: Project Overview, Sydney Metro.)

Meanwhile, additional stations are also being investigated at the Artarmon Industrial Area, Barangaroo, and either the University of Sydney or Waterloo. It remains unclear whether tunnels on the Southern end will emerge at Sydenham or whether they will emerge further North with the line then travelling along an existing reservation between Erskineville and Sydenham.

Media Coverage

VIDEO: Seven News Sydney – Electicity privatisation bill passed, Sydney Metro renaming (4/6/2015)

VIDEO: Ten Eyewitness News Sydney – Electicity privatisation bill passed, Sydney Metro renaming (4/6/2015)

Open Drum – The Daily Commute

ABC Open is taking contributions on the topic of “the daily commute”. The deadline for contributions is midday Tuesday 9 June.

“Tell us about your daily commute. What are the joys and challenges? How does it impact your life or your family? Would improved public transport, affordable accommodation near workplaces or better roads help? Whatever happened to telecommuting? Do you have a survival tip or utopian vision for policy makers? Share your story and opinions in 350-700 words.”

1 May: Rail line to Badgerys Creek downplayed

Suggestions for a fast rail service between Badgerys Creek and Sydney CBD in time for the opening of a future Western Sydney Airport were dismissed by the Federal Transport Minister Warren Truss. “A rail line connected to the metropolitan area of Sydney is not essential in that [early] phase” said Mr Truss. The NSW Transport Minister Andrew Constance was more open to the idea, stating that he was “putting all things on the table”, including a possible extension of Sydney Rapid Transit out to Badgerys Creek via the existing Kingsford Smith Airport at Mascot. Proposals exist to extend the recently opened South West Rail Link to Badgerys Creek, but there are no current plans or funding to do so.

The proposed corridors for an extension of the SWRL through to Badgerys Creek and beyond. Click to enlarge. (Source: Transport for NSW.)

The proposed corridors for an extension of the SWRL through to Badgerys Creek and beyond. Click to enlarge. (Source: Transport for NSW.)

4 May: Opal-only ticket gates

New ticket gates that accept only Opal cards are to be trialed at Olympic Park Station. Existing ticket barriers that accept both Opal and paper tickets will continue to be in use.

7 May: Mousetrap to catch graffiti vandals

A new technology is being trialed which detects either spray paint or permanent marker on trains, so far leading to the arrest of 30 individuals. Known as “Mousetrap”, it uses an electronic chemical sensor which detects the vapour of both spray paint and marker pens.  Live CCTV records and provides images directly to Sydney Trains staff. Removing graffiti from the Sydney Trains network cost $34 million last financial year, up from $30 million the year before.

10 May: Epping to Chatswood Line will be disconnected for almost a year

The Epping to Chatswood Line, set to be shut down for 7 months during which it will be converted and connected to the North West Rail Link in order to create the first stage of Sydney Rapid Transit, will be disconnected from the T1 Northern and North Shore Lines prior to its shut down. A recently approved government proposal will see the line operate as a shuttle service between Epping and Chatswood for 4 months prior to this conversion, most likely in 2018.

21 May: Light rail predicted to kill someone each year

A report prepared for the government predicts that 1.14 people will be killed by the new CBD and South East Light Rail line every year on average. Between 2010 and 2014, there have been 3 fatalities involving pedestrians and buses in the Sydney CBD. The report also predicts 1 fatality every 5 years for the existing light rail line to Dulwich Hill, although no deaths have occurred on this line since it opened in 1997.

22 May: Opal card user information handed over to government agencies

57 requests for Opal card data, which include the card user’s address and travel patterns, have been granted by Transport for NSW to government agencies since December 2014. A total of 181 requests were made, with no court approval required in order for information to be handed over. By comparison, information from Queensland’s Go Card had been accessed almost 11,000 times between 2006 and 2014.

26 May: NWRL tunneling 40% complete

Tunnel boring machines on the North West Rail Link have reached Showground Station. 12km of the 30km of tunneling, representing over a third of the total length, is now complete.

26 May: Long Bay Prison sale under consideration

The Government is considering the possibility of selling off Long Bay Prison, possibly raising a estimated $400m. The sale, which would see the site redeveloped, has been linked to a possible extension of the light rail line currently under construction. The CBD and South East Light Rail is set to open in 2019, initially reaching Kingsford. However, an extension as far as La Perouse has been raised as a possibility.

Potential extensions to the CBD and South East Light Rail to Maroubra, Malabar, or La Perouse. Click to enlarge. (Source: Infrastructure NSW, State Infrastructure Strategy Update 2014, p. 40.)

Potential extensions to the CBD and South East Light Rail to Maroubra, Malabar, or La Perouse. Click to enlarge. (Source: Infrastructure NSW, State Infrastructure Strategy Update 2014, p. 40.)

26 May: Congestion will be worse after WestConnex

Internal government reports show that traffic levels on inner city roads around the planned WestConnex tunnels are predicted to be higher in 2026 than in 2011, despite the planned completion of WestConnex by 2023. A spokeswoman for the WestConnex Delivery Authority commented that “[traffic on] the inner south will improve with WestConnex as opposed to a do nothing scenario”.

28 May: Light rail construction schedule announced

VIDEO: Ten Eyewitness News Sydney – Government admits public transport system “broken” (27/5/2015)

A construction schedule for the CBD and South East Light Rail was released to the public. George St is set to see three and a half years of construction, with the new CBD and South East Light Rail set to be built between September 2015 and April 2018. The line is currently scheduled to open in early 2019, following testing of the line.

The Opposition Leader Luke Foley, who recently declared his opposition to light rail on George St, compared the project to the Berlin Wall and declared that it would lead to chaos and confusion.

The Government released video (above) of a bus and pedestrian walking down George Street during the evening peak hour showing the pedestrian being faster than the bus. Pedestrianising George St, resulting in the replacement of cars and buses with trams, has been put forward as a way to reduce congestion for public transport users which currently exists in many parts of the city.

The announcement also included plans to defer construction on the Northern portion of the Castlereagh St bike path until construction on the light rail line is completed. The Roads Minister Duncan Gay had previously proposed including loading zones along portions of Castlereagh St, which would have the effect of making it a “part-time” bike path. Deferring its construction pushes back the need to make a decision on this issue. However, the existing bike path on College St is set to be converted into a bus lane. This will help to handle bus movements once George St becomes closed off to vehicles, but removes a North-South bike path in the CBD for a number of years.

28 May: mX axed

Newscorp is set to discontinue mX, its free commuter newspaper. mX is currently distributed each weekday afternoon in Sydney, Melbourne, and Brisbane; it began in each of these cities in 2001, 2005, and 2007 respectively.

29 May: Electricity privatisation passes lower house

Legislation to allow the 99 year lease of 49% of the NSW electricity distribution network has passed the NSW Legislative Assembly. It now goes to the Legislative Council, where a combination of the Liberal, National, and Christian Democratic Parties that have committed to supporting the legislation have enough votes to ensure its passage through the upper house of Parliament.

VIDEO: Infrastructure (Last Week Tonight with John Oliver)

Sydney Rapid Transit (SRT) could reach a new airport at Badgerys Creek, possibly via the existing Kingsford Smith airport at Mascot, as part of the Southern extension of a Second Harbour Rail Crossing. The idea was floated last week by the Transport Minister Andrew Constance when he said that “I think it is a case of putting all things on the table”, in which he also called on the Australian Government to provide funding for a rail line to Badgerys Creek. The Australian Government has committed $2.9bn in funding for roads to support the airport, but no money for rail.

The proposal is currently little more than a thought bubble. But if it were to happen, what could it look like and how would it build on existing plans that are already locked in?

The current plan

The North West Rail Link (NWRL) from Rouse Hill to Epping is currently under construction. It will be connected to the Epping to Chatswood Line, set to be closed in 2018 so that it can be converted, with the new Rouse Hill to Chatswood Line opening in 2019. Construction of a Second Harbour Rail Crossing from Chatswood to Sydenham will begin in 2017, and is expected to open in 2024. This will also see the Bankstown Line converted to single deck operation between Bankstown and Sydenham, also with a 2024 opening.

SYdney Rapid Transit following the conversion of the T3 Bankstown Line. Click to enlarge. (Source: Transport for NSW, Rebuilding NSW Fact sheet 3, p1.)

SYdney Rapid Transit following the conversion of the T3 Bankstown Line. Click to enlarge. (Source: Transport for NSW, Rebuilding NSW Fact sheet 3, p1.)

There are further plans to expand the line from Sydenham to Hurstville. Earlier plans showed the line extending from Bankstown to both Lidcombe and Cabramatta, but more recent plans show the line terminating at Bankstown and not continuing further.

Sydney Rapid Transit as currently proposed. Click to enlarge. (Source: Sandy Thomas, 1855 revisisted.)

Sydney Rapid Transit as currently proposed. Click to enlarge. (Source: Sandy Thomas, 1855 revisisted.)

Past plans

A rail line from the North West to the South West via the CBD is not a new concept. This is exactly what was proposed in 2005 as part of the Metropolitan Rail Expansion Program (MREP). This would involve the extension of the Epping to Chatswood Line via the construction of the NWRL and the extension of the then East Hills Line (now T2 Airport Line) via the construction of the South West Rail Link (SWRL). Core capacity would then be increased by building a new under the Harbour and CBD rail line, plus additional tracks from Chatswood to St Leonards; Sydenham to Erskineville; and Kingsgrove to Revesby. The difference is that the MREP proposal would use double deck trains and travel via Sydenham, therefore bypassing the existing Airport Line.

Metropolitan Rail Expansion Program. Click to enlarge. (Source: Sandy Thomas, 1855 revisisted.)

Metropolitan Rail Expansion Program. Click to enlarge. (Source: Sandy Thomas, 1855 revisisted.)

A metro line out towards Sydney’s South West was also part of a leaked 2012 report, which suggested extending SRT from Wolli Creek to Revesby. This would follow the initial conversion of the T3 Bankstown Line and then later also a portion of the T4 Illawarra through to Hurstville to the new SRT system. The latter of these two conversions passes through Wolli Creek, which would allow the portion of the T2 Airport Line to also be converted. SRT could then provide all station services on these lines, with the remaining T2 and T4 trains running express from the outer suburbs.

Previously proposed metro network for Sydney, including a line out to Revesby and the Northern Beaches. Click to enlarge. (Source: Transport for NSW, CBD Rail Capacity Program Rail Futures Investigations - Engineering & Construction, p30.)

Previously proposed metro network for Sydney, including a line out to Revesby and the Northern Beaches. Click to enlarge. (Source: Transport for NSW, CBD Rail Capacity Program Rail Futures Investigations – Engineering & Construction, p30.)

However, this proposal would not actually reach either airport.

How it could work

If both airports are to be connected then the entire T2 Airport Line would need to be converted to SRT between Glenfield and Central. The resultant shift of patronage from the T2 Airport Line to SRT together with the ability for SRT to reach the T2 Airport Line directly from Central without having to travel between Wolli Creek and Sydenham, eliminates the need to convert the T4 Illawarra Line to SRT. In fact, it would make more sense to maintain all station services from Hurstville within the Sydney Trains network and instead send them into the City Circle, joining the remaining T2 Airport Line trains (which would likely revert to the previous East Hills Line name, given they would no longer travel via the airport). This lifts the current capacity constraint on the T4 Illawarra Line, which along with the T1 Western Line is Sydney’s most congested.

The T2 Airport Line currently has 4 tracks between Wolli Creek through to Revesby in the West, where it drops down to 2 tracks. The line West of Revesby would need to be quadruplicated out to Glenfield, providing 2 tracks for T2 trains and 2 tracks for SRT trains. The Northern end of Glenfield Junction may also require some upgrading to prevent any conflicting moves between T2 and SRT trains, however the Southern end is flexible enough to be able to handle the merger of Sydney Trains and SRT services. From there it is simply a matter of converting the existing SWRL to SRT, while also extending the line out to Badgerys Creek or further.

Journeys from the SWRL would be limited to all stop services on SRT, which would probably take around 60 minutes from Badgerys Creek to Central (perhaps 45 minutes if SRT allowed for shorter dwell times and faster acceleration). Passengers could change at Glenfield with a simple cross platform transfer to a faster express train directly to Central (or elsewhere).

Meanwhile, the shutdown of the T2 Airport Line for SRT conversion could also be used as an opportunity to add an additional station (Doody St) between Mascot and Green Square and/or an additional station (Waterloo) between Green Square and Central. This would allow the Central to Sydenham alignment of SRT to take the Northern approach, via Sydney University; rather than the alternative proposal via Waterloo.

The proposed Doody St Station would be located between the existing Mascot and Green Square Stations on the Airport Line. Click to enlarge. (Source: EcoTransit.)

The proposed Doody St Station would be located between the existing Mascot and Green Square Stations on the Airport Line. Click to enlarge. (Source: EcoTransit.)

The 10km portion of the T2 Airport Line between Wolli Creek and Central is currently privately owned, but reverts to public ownership in 2030. Conversion would probably have to occur after 2030. However, with the initial Rouse Hill to Bankstown portion of SRT set to open in 2024 and an airport at Badgerys Creek set to open in 2026, the timing is not too far off the mark. Rail services would not be running on the day the airport opens, but they could commence a few years afterwards. This is problematic if the aim is rail on day one, but ideal timing if the aim is for a gradual increase in transport connections as airport usage ramps up over time.

A NSW Labor Government will build all transport projects currently under or about to commence construction plus a second Harbour rail crossing as part of its infrastructure policy released yesterday. It would also drop plans for a 99 year lease of the electricity distribution network, obtaining its $10bn funding by not cutting $5bn worth of business taxes and using $5bn of unallocated funding in the government’s Restart NSW infrastructure fund.

Under Labor, projects already under construction, such as the North West Rail Link and CBD and South East Light Rail, would be completed. Projects about to commence construction, such as the M4 East; M5 East duplication; and NorthConnex, would also be completed. In addition, Labor has also committed to the $1bn upgrade to the Western Sydney rail network, which will include improved signalling and longer platforms for trains that are 10 carriages long rather than the existing 8 carriages.

Labor will committ to completing the NWRL and has given qualified support for a second Harbour rail crossing to connect it to the CBD. Click to enlarge. (Source: Transport for NSW.)

Labor will committ to completing the NWRL and has given qualified support for a second Harbour rail crossing to connect it to the CBD. Click to enlarge. (Source: Transport for NSW.)

The plan would see both WestConnex and a second Harbour rail crossing modified. WestConnex’s M4 East would link up directly to the CBD along a yet undefined path, while the M5 East duplication would be redirected to the airport and seaport at Botany. Meanwhile, the Inner West bypass linking the M4 and M5 would be dropped entirely. Any construction on a second Harbour rail crossing would begin 5 years later than currently planned, in 2022 rather than 2017, and also be subject to a “rigorous cost-benefit analysis and business case”. In addition, no committment was made for a Western Sydney Harbour road tunnel or Western Sydney light rail.

Commentary: The wrong priorities

Labor’s refusal to consider privatisation, despite being supported by former Labor Premier Morris Iemma and Prime Minister Paul Keating, has limited its ability to promise an infrastructure plan as large as the Coalition’s. The Sydney Morning Herald’s transport reporter Jacob Saulwick put it best when he described it as “less of the same” in comparing it to the Coalition plan. In fact, other than the changes to WestConnex, this is largely a copy of the Coalition plan with some elements dropped and others deferred.

One positive to come from this report is an M5 East duplication that links up to Botany rather than St Peters. One of the main benefits of WestConnex will come from taking freight trucks off local roads, and having a direct connection will achieve this while also adding capacity to a growing port.

Labor should also be commended on committing to a second Harbour rail crossing. But deferring its construction for 5 years and adding conditions to that construction puts question marks over whether it is serious about building it. Yesterday’s policy document even quotes Nick Greiner, notorious for opposing rail projects and supporting tollroads, to make this case. In doing so, it reveals the real problem with this plan – it shifts priorities away from rail and towards roads.

Most disappointing is that this plan makes a clear committment to building a new freeway right into the CBD, while maybe building a new rail line into the CBD at a later point in the future. These are the wrong way around. Roads, which have their place, should provide travel opportunities from low density origins and/or destinations, acting as a bypass of dense areas like the CBD. Rail, on the other hand, works best at transporting large numbers of people from high density origins and/or destinations. So to build a road into the CBD but not rail is highly perverse.

WestConnex and the proposed Western Harbour road tunnel, both of which are plagued with problems like property acquisitions or of inducing demand for car travel, enjoyed the major advantage that they would remove cars from places like the Sydney CBD or Newtown’s congested King St. In the CBD, it would also see roadspace on the surface taken away from cars on George St and Elizabeth St as part of the CBD light rail line as the former is pedestrianised and the latter is converted to a bus road.

It is here, and not Labor’s inability to accelerate infrastructure construction due to it committment to maintain public ownership of state owned assets, that is most concerning. Labor prioritised roads rather than rail, and those are the wrong priorities.

VIDEO: #Equality – A short film by Neel Kolhatkar

Monday: Future of the Meccano Set uncertain

The structure holding up traffic lights and signs at the intersection of Woodville Road/Henry Lawson Drive and Hume Highway in Lansdowne, commonly known as the “Meccano Set”, could be removed. RMS is taking community and stakeholder feedback, with two possible options for the intersection:

  • repaint and maintain the structure, or
  • remove it completely and replace it with traffic signals and directional signage.

The Meccano Set was errected in 1962 and is not heritage listed, though it is considered a “place of interest” and a Western Sydney icon. Feedback will be accepted until 13 February.

Tuesday: Commuters can save by leaving car at home

Commuters could save $10,000 per year by switching from driving to taking public transport according to a report by the Australian Railway Association. The savings are contingent on not owning a car at all. Smaller savings of $1,700 per year would be possible by maintaining a car, but taking public transport to and from work rather than driving. Alan Davies at Crikey writes more on this topic.

Tuesday: SWRL appears on rail map

The South West Rail Link has appeared on the network map for Sydney Trains, while the timetable for the line has also been released. Trains will run every half hour between Leppington and Liverpool when the line opens on 8 February.

Sydney Trains network with the SWRL on the bottom left of the map. Click to enlarge. (Source: Transport for NSW.)

Sydney Trains network with the SWRL on the bottom left of the map. Click to enlarge. (Source: Transport for NSW.)

Tuesday: 524 new parking spots at train stations

Over 500 new parking spots at train stations were announced or opened this week. 400 parking spaces will be added at Holsworthy Station and 100 parking spaces will be added at Oatley Station. Meanwhile, 23 additional parking spaces were officially opened at Granville Station.

Wednesday: NWRL running ahead of schedule and under budget

The North West Rail Link is running 2 months ahead of schedule and is currently $300m under budget. The news comes as Elizabeth, the first of the 4 tunnel boring machines, reaches the future site of Norwest Station. Elizabeth began digging from Bella Vista, 2.1km away, in September of 2014.

Sunday: New ticket gates may be on the way

New, skinnier ticket barriers have been spotted at Olympic Park Station, suggesting that the current ticket barriers might be replaced soon. The barriers are currently covered up, but are clearly a more streamlined size and shape. Entry/Exit indicators have also been removed from Town Hall Station, which would also support the possibility that ticket barriers are soon to be updated.